Fill the cooling loop once and reject heat mechanically instead of by evaporation, eliminating ongoing water draw. Microsoft claims this avoids over 125 million litres per facility per year. The trade is electricity, and no operator has published the PUE penalty.
Microsoft · since 2024 · City
Microsoft announced its closed-loop, zero-water-evaporation datacentre design in December 2024, naming Mount Pleasant, Wisconsin and Phoenix, Arizona as the first sites, with further builds coming online from late 2027.…
Microsoft · 3 sources
Google, with Uruguay's Ministry of Environment · 2023–2024 · City
Google's original Canelones facility design required approximately 7.6 million litres of potable water per day for evaporative cooling. During Uruguay's 2023 drought, Montevideo's utility blended brackish estuary water…