#00222
Set a Tier 4 baseline for new generators, meter and publish runtime hours, define emergency narrowly so scheduled outages do not qualify, and enforce permits before equipment operates. Virginia adopted a 0.60 g/hp-hr baseline from July 2026.
Parent issue
#00209 Backup generators and on-site turbines add air pollution to neighbourhoods that often already fail air quality standards
Location
Description
Four requirements, applied as air permit conditions:
The health cost estimates for this equipment are driven almost entirely by runtime, not by installed capacity. Modelled Northern Virginia costs are $190 to 260 million a year at actual runtime and $1.9 to 2.6 billion if generators ran at maximum permitted levels (UC Riverside), and the state's own legislative audit finds generators are currently under 4% of regional NOx precisely because they mostly sit idle. The whole question is therefore how many hours they run, which is a permit variable and nothing else.
This is why the definition of emergency matters more than any emission factor. September 2025 DEQ guidance would reclassify utility-scheduled outages announced within 14 days as emergencies, letting dirtier Tier II units run during planned maintenance, despite research finding most facilities experience zero to two minor outages a year lasting one to five hours (Virginia Mercury). A broad emergency definition converts standby equipment into part-time power plants without any new permit.
The fourth requirement addresses a failure that has already happened at scale. xAI installed 35 turbines at its Memphis site and received a permit for 15, with satellite imagery showing at least 24 running the day before the permit issued (SELC). A permit regime that cannot count installed units before they operate is not functioning.
State environmental agencies hold the authority. The sequence that works is: adopt the Tier 4 baseline for new permits, require telemetry-based runtime reporting as a permit condition, publish the reported hours, and fund inspection capacity sufficient to verify equipment counts at commissioning. Where "temporary" or "mobile" equipment exemptions exist, close them, since that is the category the largest unpermitted installations have used.
Links
3Sub-issues
0Case studies
1