Offer faster interconnection in exchange for contractually curtailable load

#00221

Connect large loads sooner if they accept curtailment during scarcity hours. Modelling finds 76 to 126 GW of headroom in the 22 largest US balancing authorities at 0.25–1% of hours curtailed. Google has signed 1 GW of demand response but publishes no curtailment performance data.