#00225
Implements
#00220 Create a large-load tariff class with minimum take, long contract term and exit fees
Implementer
Public Utilities Commission of Ohio, on application by AEP Ohio
Timeline
Since Jul 9, 2025
Location
Description
The Public Utilities Commission of Ohio approved a dedicated tariff for data-center customers on 9 July 2025, on application by AEP Ohio. Customers at or above 25 MW must pay for at least 85% of contracted capacity regardless of actual consumption, over a 12-year minimum term with a four-year ramp. Exit fees equal three years of minimum charges, plus collateral and creditworthiness requirements apply. The instrument is a rate case requiring only regulatory approval — no new legislation. After the tariff took effect, AEP's large-load forecast fell by approximately 50%, as the take-or-pay obligation made speculative and duplicate interconnection requests expensive. Amazon, Google, Meta, Microsoft and the Ohio Manufacturers' Association opposed the tariff as discriminatory; the commission rejected rehearing and a state supreme court appeal was signalled.
Metrics
5Lessons learned
Sources
3