Case study of

#00196 Large-scale desalination sized as drought insurance

Implementer

Poseidon Water with San Diego County Water Authority

Timeline

Since Dec 1, 2015

Location

Carlsbad, California, USA33.1581, -117.3506

Description

The Carlsbad plant (December 2015) is the largest SWRO facility in the Western Hemisphere at 50 MGD, built for about $1 billion under a 30-year take-or-pay purchase agreement with San Diego County Water Authority. It delivers rainfall-independent supply but is the county's costliest source at ~$3,500 per acre-foot in 2025. The rigid take-or-pay contract produced $54M paid for unneeded water in the wet 2023–24 year and ~$35M owed for water never made during plant outages. Marine regulations forced an intake retrofit of ~$159M roughly two decades into the asset's life. Potable reuse projects in the same class cost roughly half as much per acre-foot.

Metrics

5
Plant capacity50MGD
Cost of water in 2025~3,500USD per acre-foot
Paid for unneeded water in wet 2023-2454million USD
Owed for unmade water during outages~35million USD
Intake retrofit for marine rules~159million USD

Funding

$1,000,000,000 · Private finance repaid through a 30-year take-or-pay purchase agreement

Lessons learned

  • Take-or-pay contracts bill ratepayers in wet years and even for water never made during outages: rigidity cuts both ways — negotiate flexibility triggers before signing.
  • Environmental compliance is a moving target: marine intake rules forced a ~$159M retrofit; budget for regulatory change over a 30-year asset life.
  • Where a wastewater stream exists, potable reuse of the same class costs roughly half per acre-foot: run that comparison before contracting a large desalination plant.

Documented Jul 24, 2026