El Paso, Texas, USA

#00205

OngoingCity

Case study of

#00185 Potable reuse of treated wastewater behind multi-barrier treatment and long acceptance-building

Implementer

El Paso Water

Timeline

Since Feb 27, 2025

Location

El Paso, Texas, USA31.7601, -106.4870

Description

El Paso Water broke ground on the Pure Water Center on 27 February 2025: the first US municipal direct-to-distribution potable reuse plant, sending 10 MGD of purified water straight into the distribution network with no aquifer or reservoir buffer. Capital cost is $295M (up from a $110M estimate in 2012); completion is expected in 2028. The project builds on 40 years of incremental reuse: El Paso has recharged the Hueco Bolson aquifer with reclaimed water since 1985 and operates large inland brackish desalination. Public support after sustained outreach stands at approximately 84%. Construction is underway; the plant is not yet delivering water.

Metrics

3
Direct-to-distribution capacity10MGD
Project cost escalation$110M estimate (2012)$295M at 2025 groundbreakingUSD
Public support after outreach~84%% support

Funding

$295,000,000 · El Paso Water

Lessons learned

  • Forty years of visible reuse infrastructure (aquifer recharge since 1985) normalized purified water in the public mind enough to make omitting the environmental buffer politically feasible.
  • Direct-to-distribution reuse required decades of incremental, visible steps and structured outreach before reaching the ~84% public support needed to proceed.
  • Delaying construction is expensive: the project cost nearly tripled between the 2012 estimate ($110M) and the 2025 groundbreaking ($295M), underscoring the financial risk of postponing committed projects.

Documented Jul 24, 2026