communityfix.org

Huarochirí and Canta provinces, Peru

#00203

SuccessRegion

Case study of

#00193 Revive traditional rainwater-harvesting and recharge structures through village labor and ownership

Implementer

Campesino communities with Aquafondo, The Nature Conservancy and CONDESAN

Timeline

Since Jan 1, 2015

Location

Huarochirí and Canta provinces, Peru-11.5000, -76.7000

Description

Amunas are pre-Inca infiltration canals in the Peruvian highlands that divert wet-season streamflow onto permeable slopes, where water infiltrates and resurfaces downslope months later, extending dry-season availability. Since around 2015, campesino communities in Huarochiri and Canta provinces restored these canals with facilitation from Aquafondo, The Nature Conservancy and CONDESAN. Financing flows through Peru's MERESE mechanism, which earmarks approximately 1 percent of Lima's water tariffs for upstream ecosystem services, giving mountain communities a durable revenue stream for ongoing maintenance. Approximately 86 km of canals have been rehabilitated. A 2019 dye-tracer study (Nature Sustainability) confirmed a median water residence time of ~45 days before resurfacing, and modelling suggests scaling could raise Lima's dry-season flows by ~7.5 percent.

Metrics

4
Amunas rehabilitated86km
Estimated annual rechargemore than 15 millionm3/yr
Median residence time of infiltrated water (dye-tracer study)approx. 45days
Potential increase in Lima dry-season flows at scale (modelled)approx. 7.5percent

Funding

MERESE mechanism: approximately 1 percent of Lima water tariffs earmarked for upstream ecosystem services

Lessons learned

  • The MERESE tariff mechanism (~1% of Lima water tariffs) provides upstream communities a recurring revenue stream that survives NGO exit — directly addressing the maintenance-funding gap common to recharge programs.
  • Independent hydrological quantification (dye tracers, published results) was essential to convert a traditional practice into a bankable water-supply option; replicators should budget for rigorous measurement before seeking large-scale finance.
  • The model requires a large downstream water utility with a direct financial stake in dry-season flow to anchor the payment-for-ecosystem-services mechanism; identify that anchor institution before designing the finance structure.

Documented Jul 24, 2026

Author AvatarArnaud Gissinger