Toowoomba, Queensland, Australia

#00199

FailedCity

Case study of

#00185 Potable reuse of treated wastewater behind multi-barrier treatment and long acceptance-building

Implementer

Toowoomba City Council (Water Futures proposal)

Timeline

Since Jan 1, 2006

Location

Toowoomba, Queensland, Australia-27.5600, 151.9500

Description

At the height of the Millennium Drought, Toowoomba City Council's Water Futures proposal would have added indirect potable reuse supplying ~25% of the city's water for ~A$68M. The council put it to a referendum on 29 July 2006. A developer-funded opposition group, Citizens Against Drinking Sewage, ran a visceral campaign that branded the city 'Poowoomba'; 62% voted No. The city instead built a costlier pumped pipeline from Wivenhoe Dam, completed in 2010. Documented in Hurlimann and Dolnicar (Water Research, 2010) as the canonical failure of social acceptance rather than of technology.

Metrics

3
Referendum result62% No, 38% Yes% of vote
Proposed reuse share of supply~25% of supply
Proposed project cost68million AUD

Funding

A$68,000,000

Lessons learned

  • Never put a disgust-prone technology to a referendum during an active drought: fear campaigns and visceral framing (e.g., 'Poowoomba') outrun technical reassurance even when the engineering case is sound.
  • A small, externally funded opposition group with a single memorable frame defeated the proposal decisively — plan for organised opposition with equivalent communications resources.
  • Rejection carried a real cost penalty: the replacement pipeline from Wivenhoe Dam was more expensive than the proposed reuse scheme, and the decision was never reversed.

Documented Jul 24, 2026