#00195
Case study of
#00185 Potable reuse of treated wastewater behind multi-barrier treatment and long acceptance-building
Implementer
Water Corporation of Western Australia
Timeline
Since Jan 1, 2017
Location
Description
Perth's Groundwater Replenishment Scheme at Beenyup recharges advanced-treated wastewater into deep aquifers for later drinking-water abstraction, the Southern Hemisphere's first such scheme. Capacity was doubled to 28 GL/yr in 2022 (stage 2 cost about A$262-320M). Approval was preceded by a 3-year trial, a visitor center and more than 2,500 public tours, which produced roughly 70% public support, and no referendum was held. The scheme is one pillar of a rainfall-independent supply portfolio built in response to permanent drying: streamflow into Perth's dams has fallen about 80% versus pre-1975 levels.
Metrics
4Funding
Lessons learned
Sources
2Documented Jul 24, 2026