#00143 Place PV between and on railway tracks — removable panels or solar sleepers

Erzgebirge (Ore Mountains) DB test field, Saxony, Germany

#00145

InconclusiveNational

Implementer

Bankset Energy (on Deutsche Bahn's test field)

Timeline

Since Jun 1, 2018

Location

Erzgebirge (Ore Mountains) DB test field, Saxony, Germany50.5800, 12.9800

Description

Bankset Energy tested sleeper-clip PV panels at Deutsche Bahn's Erzgebirge (Ore Mountains) test field, claiming ~0.1 MW per km and announcing 200 MW across 1,000 km in Saxony in 2018. No independent verification of the 200 MW / 1,000 km deployment has emerged. Deutsche Bahn has stated publicly that companies testing at its field do so independently of any DB adoption decision, and DB has not committed to deploying the technology.

Metrics

2
Claimed generation per km~0.1MW/km (company-claimed, unverified)
Announced deployment (2018)200 MW / 1,000 kmclaimed, unverified

Lessons learned

  • A test-field presence at Deutsche Bahn's facility does not constitute a deployment; 'is testing' and 'has built operating capacity' must be treated as distinct claims requiring separate evidence.
  • When gigawatt-scale announcements (2018) are followed by years of press silence, treat the original figures as unverified marketing until independently confirmed by third-party measurement.
  • The infrastructure host (Deutsche Bahn) explicitly not committing to adoption is a concrete signal to discount a company's rollout projections.
  • Require independently measured MWh output data, not company-stated MW/km figures, before crediting capacity claims in this technology category.